Earnings calls / TORNTPOWER · August 3, 2026

Torrent Power Ltd Q1 FY27 Earnings Call Summary

Q1 FY27 adjusted PBT fell 11.4% YoY to ₹925 crores on lower merchant gains (₹87 crores) and ₹51 crores gas upgrade costs, partially offset by distribution profit up 71% and renewables up ₹19 crores. The real driver was thermal weakness against a one-off prior-year LPS income, while Nabha Power added only five days of ₹15 crores. Management guides ~1.2 GW renewable commissioning in FY27, ₹10,000 crores RE capex, and steady-state Nabha EBITDA of ~₹1,000 crores annually. Main risks are transmission delays, tax rate stepping to 28%, and ₹20/MMBtu spot gas limiting merchant sales to peak hours.

Revenue
Margin
Demand
Guidance
Tone

Event Participants

Executives

2 Rishi Shah, Saurabh Mashruwala

Analysts

9 Apoorva Bahadur, Atul Tiwari, Harsh Singh, Mohit Kumar, Satyadeep Jain, Shirom Kapur, Sumit Kishore, Vishal, 1 Unidentified

Financials & KPIs

Metric Reported Commentary
Reported PBT ₹925 crores -₹60 crores/-6.1% YoY vs ₹985 crores; prior year included ₹59 crore non-recurring FX loss
Adjusted PBT ₹925 crores -₹119 crores/-11.4% YoY vs ₹1,044 crores adjusted; decline driven by thermal, partly offset by distribution/renewables
Effective Tax Rate 28% +300 bps YoY from 25%; increase on completion of tax holiday period under Section 80-IA for certain units
Thermal Segment Contribution -₹123 crores YoY Lower merchant gains/LNG trading (-₹87 crores) and O&M expense increase (-₹51 crores) from gas plant upgrade exercise; Nabha acquisition added ₹15 crores (5 days)
Distribution & Transmission Contribution +71% profit YoY Favourable regulatory orders (carrying cost ₹41 crores), improved operations (+₹19 crores) on higher ROE/ROCE and franchisee volumes +4%, new transmission project +₹11 crores
Renewables Contribution +₹19 crores YoY Newly commissioned capacity and improved wind/solar PLF; offset by absence of ₹46-47 crore LPS income booked in prior year
Installed Generation Capacity 6.6 GW Comprises 2.7 GW gas, 1.8 GW coal, 2.1 GW renewables as of 30 June 2026; 70 MW RE commissioned in Q1
RE Capacity Under Implementation 4.6 GW Commissioning phasing: ~1.2 GW in FY27, 1.4-1.6 GW in FY28, balance in FY29
Total Capex (Q1 FY27) ₹2,300 crores RE ₹1,550 crores, thermal ₹125 crores, transmission ₹120 crores, distribution ₹500 crores
RE Capex Incurred (Cumulative) ₹8,800 crores Against total plan of ₹29,600 crores for RE projects under implementation
Franchisee Volume Growth +4% YoY Improved volumes and increased tariff across franchisee distribution business
Merchant Power Sold 445 MUs Sold in high DAM market during peak demand periods; contribution lower by ₹87 crores YoY

Geographic & Segment Commentary

Thermal Generation (Gas & Coal): Despite elevated gas prices from Middle East geopolitical tensions, thermal maintained healthy operating margins in merchant operations, though gains from merchant sales and LNG trading fell ₹87 crores YoY. The company undertook a plant upgrade exercise at its gas-based units (O&M up ₹51 crores) to improve flexibility and availability, enabling better margins in high DAM markets and more efficient cyclical operation amid rising renewable penetration. Nabha Power acquisition (consummated 25 June 2026) contributed ₹15 crores for five days; steady-state EBITDA expected at ~₹1,000 crores annually.

Distribution & Transmission: Segment delivered 71% higher profit, driven by favourable regulatory orders approving ₹41 crores carrying cost, improved operational contribution of ₹19 crores (higher ROE/ROCE on capitalization and new tariff regulations), 4% franchisee volume growth, and ₹11 crores incremental profit from a newly commissioned transmission project. Ahmedabad circle posted 10% volume growth (in line with national average); Surat and Dahej, being industrial, showed more muted growth; DNH lower demand treated as exceptional. Agra AT&C losses rose due to absence of prior-year realization from Agra Nagar Nigam Limited.

Renewables: Segment contributed ₹19 crores positive, supported by newly recommissioned capacity and improved PLF across wind and solar, partially offset by the absence of ~₹46-47 crores LPS income booked in Q1 FY26. Operational EBITDA actually grew ₹66 crores YoY on an adjusted basis, excluding LPS. Management confirmed 70 MW commissioned in Q1, taking RE capacity to 2.1 GW.

Company-Specific & Strategic Commentary

Nabha Power Acquisition: Acquisition consummated on 25 June 2026; added ~₹6,000-6,500 crores gross debt (₹3,000 crores at Nabha, ₹3,800 crores at Torrent Power). Q1 contribution of ₹15 crores reflects only five days of consolidation. Steady-state cash-flow EBITDA of ~₹1,000 crores annually (reported basis slightly lower), with PLF running at 85%.

Gas Plant Flexibility Upgrades: Upgrade program at gas-based units to improve plant flexibility, availability, and long-term O&M costs is being progressively rolled out. These upgrades enable participation in high DAM markets where ₹20/MMBtu gas remains workable for 2-3 hours daily peak slots, and position plants competitively against battery storage once gas normalizes to $6-8/MMBtu.

Project Implementation - Anuppur Thermal (1.6 GW): PPA executed with MP Power Management Company, Letters of Award issued for BTG and balance of plant, environmental clearance received; commissioning expected in 6-7 years; ₹450 crores incurred to date.

Project Implementation - Pumped Storage Hydro (3 GW, Maharashtra): Energy Storage Facility Agreement with MSEDCL executed, Letters of Award issued for Civil & Hydro-Mechanical and Electrical & Mechanical packages; environment and forest clearance received; commissioning in 3-4 years; ₹1,130 crores incurred to date.

AMGEN Replacement Plant: State government approved coal allocation for a proposed ~800 MW replacement unit for the 362 MW AMGEN plant (which has permission to operate until December 2030). Central government coal allocation pending; land location not yet finalized, possibly outside Gujarat.

Capex Program: FY27 RE capex guided at ~₹10,000 crores; Q1 RE capex of ₹1,550 crores vs ₹335 crores in Q1 FY26 and ₹1,200 crores in Q4 FY26, reflecting accelerated execution.

Bidding Philosophy: Company restricts bidding to achieve mid-teen IRR thresholds; participating in almost all major tenders but prioritizing value over capacity growth.

Guidance & Outlook

Metric Guidance / Outlook Commentary
RE Commissioning (FY27) ~1.2 GW Q2 expected ~400 MW, H2 expected ~800 MW; phasing tied to transmission availability
RE Commissioning (FY28) 1.4-1.6 GW Balance of 4.6 GW pipeline commissioned in FY29
RE Capex (FY27) ~₹10,000 crores Q1 incurred ₹1,550 crores; aligned with commissioning schedule
Nabha Power EBITDA ~₹1,000 crores/annum steady state Cash-flow basis; PLF ~85%; reported EBITDA slightly lower
Anuppur Thermal (1.6 GW) Commission in 6-7 years PPA executed, BTG/BoP letters awarded, environmental clearance received
Pumped Storage Hydro (3 GW) Commission in 3-4 years ESFA with MSEDCL executed, E&M and Civil packages awarded
Solapur Transmission Commission in FY27 ₹330 crores cumulative capex incurred to 30 June 2026
LNG Sourcing 10 cargoes contracted at Brent-linked pricing Spot cargoes (~$20/MMBtu) too expensive; three summer cargoes already imported

Risks & Constraints

Risk Context
Elevated LNG Spot Prices Spot gas at ~$20/MMBtu makes merchant operations challenging; management selling only in high DAM market 2-3 hours daily. Mitigation: Brent-linked contracted cargoes, flexibility upgrades, expected normalization to $6-8/MMBtu over horizon.
Transmission Infrastructure Delays ROW issues and PGCIL transmission line schedules are delaying multiple RE project commissioning timelines; management plans execution to coincide with line availability, but FY27 target of ~1.2 GW carries execution risk.
Renewable Project Timelines Several projects (SECI XII, SECI XVI wind, hybrid projects) extended into FY28; delays driven by transmission infrastructure, not internal execution issues.
Tax Rate Normalization Effective tax rate increased from 25% to 28% on completion of Section 80-IA tax holiday for certain units; this is a structural step-up, impacting reported profitability on an ongoing basis.
AT&C Loss Variability Agra circle AT&C losses rose year-on-year due to absence of prior-year realization from Agra Nagar Nigam Limited; treated as exceptional but contributes to quarter-over-quarter volatility.
Demand Softness in Industrial Circles Surat, Dahej and DNH volume growth muted versus national average; DNH specifically flagged as exceptional, but industrial-area demand is structurally lower growth than residential.

Q&A Highlights

Nabha Power Economics and Debt

  • Question: Can you share Nabha Power's revenue, adjusted EBITDA for Q1, and post-acquisition gross debt position? Is ₹250 crores EBITDA per quarter sustainable? (Mohit Kumar, ICICI Securities)
  • Answer: Only five days of income booked (~₹15 crores profit) since acquisition closed on 25 June; gross debt added ~₹6,000-6,500 crores (₹3,000 crores in Nabha books, ₹3,800 crores in Torrent Power books). Steady-state cash-flow EBITDA of ~₹1,000 crores annually is a good estimate; reported basis slightly lower. (Saurabh Mashruwala, Rishi Shah)

Renewable EBITDA Differential and LPS Income

  • Question: Why is renewable EBITDA only ~₹20 crores higher despite 30% generation growth? (Mohit Kumar, ICICI Securities)
  • Answer: Prior year Q1 included ₹46-47 crores of LPS (late payment surcharge) income that is not available this year; excluding LPS, renewable EBITDA is actually higher by ~₹66 crores. LPS income was a one-time item in Q1 FY26 only. (Saurabh Mashruwala)

Distribution Demand and AT&C Losses

  • Question: Ahmedabad grew 10% but Surat, Dahej, DNH were muted; AT&C losses increased across circles. What's driving this? (Satyadeep Jain, Ambit Capital)
  • Answer: Ahmedabad growth is comparable to national average; Surat and Dahej are industrial towns with structurally lower growth. DNH lower demand is exceptional, not repetitive. Agra AT&C losses increased materially only because prior year had a large realization from Agra Nagar Nigam Limited; DDDNH and SMK are not materially different from last year. (Saurabh Mashruwala)

Merchant Market Outlook and Gas vs. Battery Competition

  • Question: With large untied capacity and rising BESS installations, how do you evaluate merchant gas potential and the risk from battery storage? (Satyadeep Jain, Ambit Capital; Apoorva Bahadur, IIFL)
  • Answer: Peak and summer evening demand are prolonging, providing ongoing merchant opportunities. Once gas normalizes to $6-8/MMBtu, variable cost of ~₹4-4.5/kWh would be competitive versus battery storage (solar ₹2-2.5 plus battery ₹3 = ₹5-5.5/kWh). Merchant sales of 445 MUs in Q1 were primarily in high DAM market. (Saurabh Mashruwala)

RE Commissioning Phasing and FDRE Project Delays

  • Question: Is the 1.2 GW FY27 commissioning target back-ended? Are STU/transmission delays affecting specific projects? (Sumit Kishore, Axis Capital; Shirom Kapur, Jefferies)
  • Answer: Q1 commissioned 70 MW; Q2 expected ~400 MW, H2 balance ~800 MW. Delays in some projects are due to transmission line availability and ROW issues; management coordinates with transmission utilities but guided that after factoring in all issues, the 1.2 GW target remains achievable. (Saurabh Mashruwala, Rishi Shah)

AMGEN Replacement Plant (800 MW)

  • Question: Media reports suggest shifting the AMGEN plant and setting up an 800 MW replacement. What is the official status? (Sumit Kishore, Axis Capital)
  • Answer: AMGEN is 362 MW with permission to operate until December 2030. Company requested double coal allocation (from state) for a ~800 MW unit to replace AMGEN for Ahmedabad distribution. State government has approved coal allocation; central government approval is pending. Land location not finalized, and the plant may not be in Gujarat. (Saurabh Mashruwala)

C&I and Data Center Tie-ups for Gas Plants

  • Question: Any plans to tie gas plants to data centers or C&I customers for firm power? (Apoorva Bahadur, IIFL)
  • Answer: C&I customers prefer renewable power (RTC); gas does not fit into that category. Data centers also favor renewables. Key constraint: gas prices cannot be hedged long-term, so locking a fixed-price PPA carries inherent tariff risk. No plans in the short-to-medium term. (Saurabh Mashruwala)

LNG Sourcing and Pricing

  • Question: What is LNG availability and landed price, given the contracted cargoes from the last call? (Atul Tiwari, JP Morgan)
  • Answer: Three cargoes contracted for summer were imported and used to meet distribution demand. Balance period relies on spot cargoes selectively when opportunity is affordable. Ten cargoes are contracted at Brent-linked rates (not spot). Spot at ~$20/MMBtu is unaffordable for PPA-linked sales; purchases planned to keep margins reasonable in merchant market. (Saurabh Mashruwala, Rishi Shah)

Gas Plant Economics at $20/MMBtu

  • Question: At $20/MMBtu (variable cost ~₹30/kWh), how are you able to sell? Is there still demand, or are cargoes cheaper? (Vishal, PL Capital)
  • Answer: At $20, sales only work in high DAM market (not regular market capped at ₹10). Plant flexibility upgrades enable cyclical operation with frequent start/stops and 2-3 hours of daily peak pricing; however, high PLF operation is not possible at $20 — the price is quite challenging. (Saurabh Mashruwala, Rishi Shah)

Franchisee Pipeline

  • Question: Any new franchisee opportunities in the pipeline, particularly in UP? (Harsh Singh, Sameeksha Capital)
  • Answer: UP franchisees will likely come post-election given prior agitation issues; state subject. Maharashtra is a possible opportunity, but nothing concrete on the franchisee side currently. (Saurabh Mashruwala)

Key Takeaway

Torrent Power reported Q1 FY27 adjusted PBT of ₹925 crores, down 11.4% YoY on an adjusted basis, with thermal contributing negatively (-₹123 crores) due to lower merchant gains (₹87 crores) and one-off gas plant upgrade costs (₹51 crores), while distribution & transmission (+71% profit) and renewables (+₹19 crores) partially offset the decline. The Nabha Power acquisition closed on 25 June and is expected to add ~₹1,000 crores steady-state cash-flow EBITDA annually. Installed capacity stands at 6.6 GW, with 4.6 GW of renewable capacity under implementation and a ₹10,000 crore FY27 RE capex plan; commission phasing implies ~1.2 GW in FY27 (Q2: 400 MW, H2: 800 MW), 1.4-1.6 GW in FY28. Gas-based merchant strategy is being repositioned through plant flexibility upgrades to capture high DAM market slots even at elevated $20/MMBtu prices, with management confident of competitiveness versus battery storage once gas normalizes to $6-8/MMBtu. Key watch items include transmission infrastructure delays impacting renewable commissioning timelines, tax rate normalizing to 28% on expiry of 80-IA benefits, and AT&C loss volatility in Agra; the 800 MW AMGEN replacement plant awaits central coal allocation approval.

What you get with InvestorStack

Institutional-grade research, built for individual investors.

  • Research Reports for every listed Indian company
  • Detailed valuation models
  • Growth triggers, Risks, KPIs, Read between the lines
  • Scans, One pagers, Industry research reports
Try for free