Earnings calls / CRAFTSMAN

Craftsman Automation Limited Q1 FY27 Earnings Call Summary

Craftsman Automation's Q1 FY27 call centered on capacity expansion and the heavy horsepower engine ramp rather than detailed financials, which were not prese...

Revenue
Margin
Demand
Guidance
Tone

Event Participants

Executives

1 Srinivasan Ravi

Analysts

6 Chandra Muthiah, Joseph George, Mukesh Saraf, Mumuksh Mandlesha, Shagun Beria, Vignesh SBK

Financials & KPIs

Transcript incomplete - detailed Q1 P&L (revenue, EBITDA, profit) not presented on the call; metrics below are those discussed by management.

Metric Reported Commentary
Consolidated CapEx plan (FY27) ~₹1,500 crore Standalone ~₹1,000+ crore, DR Axion ₹430 crore (approved, phased), Sunbeam maintenance-only; upward revision possible if Q2-Q3 demand traction sustains
Alloy wheel installed capacity 9.8 million wheels FY27 production expected to touch/cross ~4 million wheels across Kothavadi and Shoolagiri; marginal capacity expansion planned only after crossing 80% utilization threshold
Powertrain capacity utilization ~70% Festive-season peaks of 75-80% are short-lived; >70% annualized seen as difficult due to seasonality and risk of stopping customer lines; operating ~10% below optimum
Aluminum capacity utilization >80% Highest across segments; growth expected to beat all other segments for several quarters on maturing capacities and new orders
Depreciation (annualized) ~₹500 crore Reflects large installed base; replacement/maintenance CapEx of ₹250-300 crore required annually at current cost levels
Heavy HP engine revenue target $100 million by FY29-30 First four customers already fill initial target; 30% productionized by FY28, 50% by FY29, full revenue visible only in FY30
Sunbeam top line impact -10% to -20% revenue From exiting legacy low-margin businesses; gross margin/value-add will rise as product mix shifts

Geographic & Segment Commentary

  • Aluminum: On a clear growth path with massive recent investments; some capacities still maturing. Portfolio is four-wheeler heavy, closely followed by two-wheeler, with both growing. New orders split between quick wins (production from FY27-FY28) and development-stage programs (production in FY28-FY29, largely FY29). Utilization at >80%, highest across segments.

  • Powertrain (incl. heavy HP engines): Utilization averaging ~70%, rising to 75-80% only during festive season. Conventional powertrain carries ~70-75% weightage of current EBIT margins. Heavy HP engine casting at Kothavadi foundry is in capacity build-up; machining and billing happen at the Arasur plant. The $100 million revenue target for FY29-30 is on track, and fresh inquiries could extend it beyond the initial projection into FY30-31.

  • Industrial Engineering (material handling & storage): Demand upswing in both lifting equipment and storage divisions, driven by the India CapEx cycle. Not CapEx-intensive, so operating leverage is expanding margins; order intake increasing quarter-on-quarter - not a one-off spike.

  • Sunbeam: Restructuring ~90% complete by December 2026, with exit-part delays due to customer requests for continued support. Exiting legacy (10-20-year-old) negative-margin businesses; replacing volumes with parent-sourced orders and new customers. Q4 FY27 EBITDA margin expected in line with the Craftsman business.

  • DR Axion: Substantial CapEx underway; land purchased last year. Incremental orders received beyond initial wins, with production starting FY29 and FY30 in general. CapEx pacing will adjust to order traction.

Company-Specific & Strategic Commentary

  • Heavy horsepower engine supplier validation: Six large customers engaged - orders received from five, sixth receiving shortly. First four customers alone fill the initial $100 million target (casting + machining). Two customers are in pilot-lot machining with parts in production use; casting validation takes ~1 more year. With supplier-acceptance passed, incremental orders from same customers will convert in ~2 years versus the initial 4-year timeline.

  • Hosur Unit 3: New high-pressure die casting facility for automotive parts (two- and four-wheeler) - not alloy wheels. Driven by space and capacity constraints at existing plants; will be filled with customer orders as they come, built in phases over 5-6 quarters.

  • CapEx inflation & funding: Recreating the same capacity as 2016 costs 5-7x more (land up 8-9x, construction 3-4x, machinery ~2x in INR terms). Greenfield basic infrastructure (land, building, ETP, HT, power, roads) runs ₹100-250 crore before production equipment. All CapEx to be funded from internal accruals; no public market raise needed; net debt-to-EBITDA on track.

  • Material cost pass-through: Raw material prices rose sharply; pass-through varies by customer - some adjusting fairly, others slow. Management is confident all customers will align to the new reality of fair supplier compensation for raw material costs.

  • Land acquisition: Close to signing a deal (no further details provided).

Guidance & Outlook

Metric Guidance / Outlook Commentary
Sunbeam EBITDA margin In line with Craftsman business by Q4 FY27 Restructuring ~90% complete by December; exiting negative-margin products lifts margins even as top line falls 10-20%
Heavy HP engine revenue $100 million by FY29-30; upside possible by FY30-31 30% productionized in FY28, 50% in FY29, full revenue in FY30; new order wins will convert faster (~2 years) from established relationships
Consolidated CapEx ~₹1,500 crore for FY27, possible upward revision Board to decide in Q3/Q4 based on Q2-Q3 traction; original plans assumed an Iran-crisis-driven slowdown
Alloy wheels Cross ~4 million wheels in FY27; marginal capacity expansion Combined Kothavadi + Shoolagiri; expansion only after crossing the 80% utilization threshold
Aluminum growth Outpace all other segments for several quarters Capacities from recent investments still maturing; strong new-order pipeline

Risks & Constraints

Risk Context
Material cost inflation Input prices rose sharply in Q1; pass-through timing varies by customer, with some slow to adjust. Management is confident of eventual recompense, but near-term margin pressure is possible until agreements align.
Geopolitical / global slowdown Iran crisis cited as the reason CapEx plans were conservatively set; management is in wait-and-watch mode. If global manufacturing traction stalls, spend could be deferred; if it accelerates, CapEx could be revised upward in Q3/Q4.
New capacity ramp-up drag Kothavadi foundry and DR Axion are under-utilized during build-up; EBIT margins on these portions will look depressed until operating leverage sets in. Management expects return ratios to align with current powertrain within ~2 years.
Sunbeam transition Customer-requested delays in exiting legacy parts push full restructuring to December; top line declines 10-20% in the interim, with goodwill support extended to exiting customers.
Powertrain seasonality Utilization swings between ~70% and 80% through the year; sustaining >70% annualized is difficult, capping revenue upside from existing capacity without new orders.

Q&A Highlights

Segment outlook (Aluminum, Industrial)

  • Question: What is driving the strong aluminum revenue/EBIT growth, and what is the order outlook? (Mumuksh Mandlesha)
  • Answer: The earlier trend was muted - Q1 has returned to normal, and the growth journey will continue, beating all other segments due to massive recent investments and maturing capacities. Portfolio is four-wheeler heavy, closely followed by two-wheeler. Quick order wins land in FY27-FY28; development-stage orders enter production in FY28-FY29, mostly FY29. (Srinivasan Ravi)
  • Question: What drove the industrial segment spike this quarter? (Chandra Muthiah)
  • Answer: Contract manufacturing is steady; material handling and storage divisions are seeing a demand upswing from the CapEx cycle. Not CapEx-intensive, so operating leverage supports margins; orders are increasing quarter-on-quarter - not a one-off spike. (Srinivasan Ravi)

Heavy horsepower engines

  • Question: How long is the prove-out/certification timeframe before full production with new customers? (Chandra Muthiah)
  • Answer: Six large customers engaged; orders from five, sixth shortly. First four alone fill the $100 million FY29-30 target. Two customers are in pilot-lot machining with parts in production use; casting validation needs ~1 more year. 30% productionized by FY28, another 50% by FY29, full revenue in FY30. Since supplier-acceptance is passed, new incremental orders will convert in ~2 years, not 4. (Srinivasan Ravi)
  • Question: What is the margin profile of the heavy HP engine business versus current powertrain, and are there startup costs? (Chandra Muthiah)
  • Answer: Current powertrain EBIT carries >70-75% weightage from conventional powertrain. Depreciation for large engine investments and development costs are already factored into powertrain results - the worst of startup absorption is over. New capacity with lower utilization will show depressed EBIT until operating leverage sets in, but return ratios should align with current powertrain within ~2 years. (Srinivasan Ravi)

CapEx plans and funding

  • Question: What is the FY27 CapEx split across entities, and what is Hosur Unit 3 for? (Mukesh Saraf)
  • Answer: Sunbeam - maintenance/some capacity CapEx only. DR Axion - ₹430 crore approved, phased, may spill into next year. Standalone - averaging over ₹1,000 crore. Hosur is not alloy wheels; it is additional high-pressure die casting capacity for automotive parts (2W and 4W), set up proactively as current plants run out of space, phased over 5-6 quarters based on demand. (Srinivasan Ravi)
  • Question: Should we assume ~₹1,500 crore consolidated CapEx for FY27? (Joseph George)
  • Answer: Conservatively, yes. Plans were made assuming the Iran crisis would slow activity; if Q2-Q3 traction continues, the board may decide in Q3/Q4 to increase CapEx at the tail end. (Srinivasan Ravi)
  • Question: Where is the standalone ₹1,000 crore going, and is funding from internal accruals? (Vignesh SBK)
  • Answer: Greenfield infrastructure costs ₹100-250 crore per plant before production equipment; customers are announcing large greenfield projects and expect supplier investments. Same capacity as 2016 now costs 5-7x more (land 8-9x, construction 3-4x, machinery ~2x in INR terms). Maintenance CapEx alone is ₹250-300 crore. Funding is entirely from internal accruals; net debt-to-EBITDA is on track; no public market raise needed. (Srinivasan Ravi)

Sunbeam restructuring

  • Question: How large is the business being exited, and what is the margin impact? (Joseph George)
  • Answer: Exiting legacy businesses (10-20 years old, some partly outsourced to tiny scale industries) with negative margin profiles. Volumes are being replaced by new customers and parent-sourced orders, so capacity stays utilized. Top line may fall 10-20%, but value-add/gross margin increases. Q4 FY27 EBITDA margin should be in line with Craftsman business. Exits are delayed a few months due to customer requests for handholding - goodwill support during transition. (Srinivasan Ravi)

Capacity utilization

  • Question: What are current capacity utilizations by segment? (Shagun Beria)
  • Answer: Powertrain ~70% average; festive season peaks 75-80% briefly, then Q3 comes down and Q4 rises again. Sustaining >70% annualized is difficult due to seasonality and customer-line risk; operating ~10% below optimum. Aluminum is already >80%. (Srinivasan Ravi)

Heavy HP revenue timing and land update

  • Question: Confirm 30% revenue from FY28 and 50% from FY29; and any land update? (Vignesh SBK)
  • Answer: FY27 is too small to talk about; decent revenue starts FY28 onwards. The full $100 million will be tested in FY30, with potential upside from new order wins. On land, something is happening - close to signing a deal. (Srinivasan Ravi)

Key Takeaway

Craftsman Automation's Q1 FY27 call centered on capacity expansion and the heavy horsepower engine ramp rather than detailed financials, which were not presented on the call. Management described aluminum growth as clear and ahead of other segments for many quarters at >80% utilization, while powertrain ran at ~70% with seasonal peaks. The stationary/heavy HP engine program remains on track for $100 million revenue by FY29-30: orders secured from five of six large customers, pilot-lot machining underway for two, with 30% productionized by FY28 and 50% by FY29. Consolidated CapEx of ~₹1,500 crore (standalone ₹1,000+ crore, DR Axion ₹430 crore) is fully funded from internal accruals, with possible upward revision if Q2-Q3 traction persists. Sunbeam restructuring is ~90% complete by December, targeting Craftsman-level EBITDA margins by Q4 FY27 despite a 10-20% top-line decline. Key watch-points include material cost pass-through timing, ramp-up drag at new plants, and the board's Q3/Q4 CapEx decision.

What you get with InvestorStack

Institutional-grade research, built for individual investors.

  • Research Reports for 1,800+ companies
  • Detailed valuation models
  • Growth triggers, Risks, KPIs, Read between the lines
  • Scans, One pagers, Industry research reports
Try for free