Initial energization of the Amazon-linked data-center load at Comanche Peak nuclear site by end-2027, with full ramp by late 2032.
Start of contracted nuclear capacity deliveries to Meta at Perry and Davis-Besse in December 2026 and December 2027.
Commissioning of two new West Texas natural-gas units totaling 860 megawatts in early to mid-2028.
Development of the Helix Digital Infrastructure platform as a new data-center power-solutions channel for Vistra.