Valero expects the St. Charles FCC unit optimization project to be completed in Q3 2026, increasing production of high-value products such as alkylate and finished gasoline.
Valero expects the Port Arthur DHT unit to be repaired and returned to service by year-end 2026, restoring a distillate-hydrotreating capability.
Valero is pursuing ethanol debottlenecking projects totaling 100 million to 200 million gallons per year, expected to come online within the next one to two years.
Valero expects processing rates of Venezuelan heavy crude to exceed its historical maximum in the coming months, leveraging Gulf Coast heavy-crude processing capability.
Valero expects near-record processing of weakened California crude at its Wilmington refinery in the coming months.