Duane Arnold nuclear plant is expected to return to service no later than Q1 2029 after NextEra completed ownership and regulatory steps.
FPL expects to announce at least one large-load transaction under its tariff by the end of 2026, with 12 GW in advanced discussions and possible service starting in 2028.
NextEra is advancing up to 9.5 GW of gas-fired generation projects in Texas and Pennsylvania tied to the U.S.-Japan large-load program, with definitive agreements still being negotiated.
FPL is on track to install about 900 MW of solar and more than 1.4 GW of battery storage during 2026.
NextEra expects its proposed combination with Dominion Energy to close in the second half of 2027, creating a larger platform for regulated growth.