Analysis: Vedanta Power Ltd

NSE:VEDPOWER Power Generation & Supply Market cap: ₹13.9K cr

Growth thesis

Vedanta Power sells electricity from 4.2 GW of coal-fired thermal capacity, mostly to state distribution companies, and was carved out of Vedanta Ltd into a standalone listed entity on 1 May 2026. The business economics are those of a contracted utility with two controllable levers: how much of the fleet is available, and what the coal inside it costs. Management said on the Q2 FY27 call that about 74% of capacity is tied up through long-term power purchase agreements and that roughly 85% of coal requirement is secured through long-term linkages, with a stated target of 85 to 90% of capacity under long-term or medium-term contracts. That structure means earnings move mainly on plant availability, fuel cost and the price achieved on the uncontracted remainder, not on demand discovery.

The first lever moved sharply this year. Domestic coal at Meenakshi went from 65-70% of consumption in Q1 FY27 to 87% in Q2 FY27 and 95% in September, and management said the plant is 'very near to reach 100% number now'. The reported consequence: realisation of about INR 6 per unit against an overall cost of INR 5, where imported coal at current prices would have meant INR 7, and an estimated INR 127 crore saved in the quarter versus imported coal. This is a reported outcome, not a forecast, and it converts a globally priced input into a domestic procurement task with linkage cover behind it. The residual imported share and the reliability of Indian coal supply and rail logistics are the conditions attached to it.

The second lever is availability, and it is where the turnaround case actually sits. A boiler incident took Shakti Unit 1 out of service and produced a INR 487 crore exceptional item that pushed Q1 FY27 reported PAT into loss. The unit has returned: management said supply began on 25 September 2026 and the unit was synchronised to the grid on 25 October 2026. Shakti is now supplying a medium-term Tamil Nadu tender at INR 5.50 per unit, with tie-ups in Maharashtra and other states at better realisation, and about 100 MW of open Athena capacity was selling at INR 5 to INR 6 and above. Q2 FY27 consequently delivered record revenue of INR 2,908 crore, up 38%, and record EBITDA of INR 421 crore, up 122% and 45% above Q1 FY27, with PAT before exceptional items of INR 101 crore against a INR 142 crore loss and a first positive EPS of INR 0.21. Of that EBITDA, INR 58 crore was a one-time recovery of legacy ash disposal cost under an OERC judgment; stripping it out, EBITDA of roughly INR 363 crore is still up about 89% year on year. That arithmetic is mine, not management's.

The next milestone is Shakti Unit 2, and it is the one that decides the shape of FY28. Project progress was 70% at end-Q2 FY27, startup is planned in Q4 FY27, and management said commissioning activity would begin by end of the year and that it was confident of holding the guidance. Around INR 1,200 crore of Shakti capex remains, to be spent in H2 FY27 and part of Q1 FY28. Completing the unit takes operating capacity from 4.2 GW to 4.8 GW on a portfolio where three quarters of capacity is already contracted. Management's guidance is that net debt to EBITDA moves from 4.47 times, itself down from 9.82 times a year earlier, to around 2 times once the unit operates. Guidance and inference should be kept apart here: the 2 times figure is a management expectation, while the 4.47 times is a reported number.

Capital allocation is the part of the story that is still mostly stated intention. The CFO listed the priorities as working capital and cost discipline, continued deleveraging, and deploying growth capital only against projects with secure offtake and appropriate returns. The only new project with disclosed economics is a 1,600 MW bid, two 800 MW units, into a 4,000 MW Uttar Pradesh tender with results expected in about two months, at a pithead site where management estimates variable cost near INR 2.5 per unit and says tariffs above INR 6 per unit would give comfortable returns and payback under six years. The larger ambition was described as 'our aspiration to go up to 13 gigawatt', with land still under identification and the matter to go to the board. Separately, management said leverage of 10 to 12 times would support around four 800 MW units. None of that is approved, costed or dated, and the ranking aim of moving from the fifth to the third largest private player within five years is an ambition.

On delivery, the record is short and should be described as such. One dated commitment came due in this bundle: Unit 1 by end of Q2 FY27, which was met. Unit 2 guidance was reaffirmed, the 100% coal target is progressing, and the ash cost recovery converted into INR 58 crore of cash. The INR 300 crore short-supply refund recorded in Q1 FY27 research received no update and the insurance claim remains under assessment, so neither can be credited. With one transcript available, this is not a management track record; it is a single on-time delivery plus several open items.

What would falsify the thesis is concrete. Unit 2 slipping materially past Q4 FY27 while the remaining INR 1,200 crore is spent would leave the 4.8 GW base undelivered and net debt to EBITDA above the path management has sketched. Domestic coal stalling short of 100%, or logistics forcing imports back into the mix, would undo part of the INR 127 crore saving and push Meenakshi's cost back toward the INR 7 imported equivalent. Short-term tariffs softening before the 74% contracted share reaches 85-90% would compress revenue on the uncontracted quarter of capacity. And a repeat outage at any single plant would swing consolidated results the way the Q1 FY27 incident did, because earnings and the entire near-term growth plan rest on Shakti and Meenakshi. The other falsifier is capital allocation: acting on leverage of 10-12 times to build four 800 MW units would raise debt sharply from INR 7,444 crore before those units earn anything.

The valuation work in the bundle is a Q1 FY27 projection with no exit multiples and is not refreshed here, so no conclusion is drawn about what is priced in. The thesis rests on delivered capacity, a measurable fuel cost shift and a deleveraging path that has already halved net debt to EBITDA, against a growth pipeline whose dates and funding remain uncommitted.

Why is Vedanta Power Ltd stock rising?

  • The unit that was sidelined by the boiler incident is generating again: management said supply began on 25 September 2026 and the unit was synchronised to the grid on 25 October 2026. It now feeds a medium-term Tamil Nadu tender at 5.50 per unit, with tie-ups in Maharashtra and other states at better realisation, plus about 100 MW of open Athena capacity selling at 5 to 6 and above. The 487 crore exceptional charge was an FY27 event, not a recurring cost.
  • Domestic coal reached 87% of Meenakshi's consumption in Q2 FY27 and 95% in September, from 65-70% in Q1 FY27, saving an estimated 127 crore versus imported coal in the quarter. Realisation was about 6 per unit against an overall cost of 5, where imported coal at current prices would have meant 7. The remaining gap to 100% converts a volatile global input into a domestic procurement task with long-term linkage cover behind it.
  • Unit 2 stood at 70% project progress at end-Q2 FY27 with startup planned in Q4 FY27 and about 1,200 crore of Shakti capex still to spend across H2 FY27 and part of Q1 FY28. Completing it takes operating capacity from 4.2 GW to 4.8 GW on a portfolio where 74% of capacity is already under long-term PPAs. Management expects net debt to EBITDA to move from 4.47 times to around 2 times once the unit runs, converting sales growth into a stronger balance sheet rather than only more revenue.
  • Management states 74% of capacity is tied through long-term PPAs and targets 85 to 90% in long-term or medium-term contracts, keeping the balance for a short-term market it describes as favourable on shortage across India. Unit 2 output will initially be sold into the exchange before contract tie-ups, and management said it intends to cover balance capacity at Meenakshi and Athena in the same window. Progress here converts uncontracted megawatts into visible revenue.
  • Management estimates a brownfield unit next to its coal source, 60-70 km from the mine, would carry variable cost of about 2.5 per unit, and says recent tenders at 6 or above would deliver a comfortable ROE with payback under six years. The company bid 1,600 MW of a 4,000 MW Uttar Pradesh tender with results expected in about two months, is participating in West Bengal, and aims to move from the fifth to the third largest private player within five years. No capital cost or approval has been disclosed.

Research report

companyname: Vedanta Power Limited ticker: VEDPOWER sector: Power / Thermal Power Generation Vedanta Power is the thermal power generation business carved out of Vedanta Ltd through the demerger that became effective on 1 May 2026, making the company a standalone listed entity. Management's stated rationale for the spin-off was "greater strategic focus, sharper accountability and a stronger platform for long term value creation in power sector." That is the governance reason the business exists...

Read the full report →

Catalysts

capex, margin expansion, debt reduction

Growth guidance

Management retains Q4 FY27 startup for Shakti Unit 2, with commissioning activity beginning by end of the year and the guidance 'we still hold on to'. It targets 100% domestic coal at Meenakshi within the year and 85-90% of capacity under long-term or medium-term PPAs, and expects net debt to EBITDA to move to around 2 times once Unit 2 operates. The 13 GW capacity figure is described as an aspiration still under land identification, not a dated commitment.

Get valuation models, detailed research reports, thematic primers, risk analysis, growth triggers, bear case, capex tracker, walk the talk, and more for Vedanta Power Ltd and 4,900+ companies.

Sign in
5-day free pass. No card required.