Analysis: Laser Power & Infra Ltd

NSE:LASERPOWER Cables - Power Market cap: ₹3.8K cr

Growth thesis

Laser Power & Infra runs two integrated businesses in India's power transmission and distribution chain: manufacturing of cables, conductors and specialty products, and EPC of power distribution infrastructure that consumes its own output. Q2 FY27 revenue from operations was approximately INR628 crores, up 2.1% year on year and 20.5% sequentially, with manufacturing at INR524 crores (+29.9%) and EPC at INR104 crores (-51% on rain-delayed execution). EBITDA was INR76 crores at a 12.1% margin and PAT INR31 crores. H1 FY27 revenue was approximately INR1,150 crores (+7.5%) with PAT of INR52 crores. The order book was approximately INR2,543 crores at September 30, 2026, split approximately INR1,303 crores manufacturing and INR1,240 crores EPC, and management guides FY27 EBITDA margin to 12.5-13%, with about 40-42% of full-year revenue typically booked in H1.

The persistence of these economics rests on specialised, qualified products rather than volume. Manufacturing mix is guided at 80-90% cable and 10-15% conductor, with conventional conductor the lowest-margin line, and management's stated strategy is to shrink the conventional conductor base in favour of specialised grades. The proof point arrived in Q2 FY27: Power Grid awarded a contract aggregating INR72.76 crores for HTLS conductors and re-conducting of existing transmission lines, Laser's first commercial HTLS order, after roughly 18 months of product testing, qualification and execution readiness under its licensing agreement with TS Conductors of the USA. In the same quarter CESC awarded a INR44 crores EPC contract for 33 kV and 220 kV underground cabling, Laser's first 220 kV underground transmission project, with roughly one year of execution. Management framed both as moving the company from distribution-grade products into high-voltage transmission.

This is not an uncontested position. Re-conductoring tenders are open to all qualified technologies, and management acknowledged competition on price while arguing the newer-generation technology carries cost advantages. The first HTLS order of INR72.76 crores is small against the approximately INR1,250 crores of tenders the company had bid into, and no conversion expectation was given for the remainder. If follow-on awards do not arrive, the mix shift relies on high-voltage cables and the specialised conductor line stays too small to change blended economics.

The capital-structure lever is now live. Approximately INR490 crores of IPO proceeds repaid borrowings during Q2 FY27, leaving total borrowings of approximately INR499 crores on September 30, 2026. Q2 finance cost was approximately INR33 crores versus INR36 crores in Q1 FY27 and INR34 crores in Q2 FY26, capturing only a partial-period benefit; management expects the saving to reflect more fully in H2 FY27 and, with better operating performance, to support PAT margin improvement. This matters because finance cost has historically absorbed a large share of EBITDA and compressed the conversion of operating profit into PAT.

The balance sheet is the constraint to watch. Working capital stood at approximately INR1,159 crores at September 30, 2026 against approximately INR1,059 crores in Q1 FY27, with working capital days improving to 166 from 183 but inventory rising to approximately INR946 crores from INR710 crores on execution delays. Management targets a 25-40 day reduction in working capital days by Q4 FY27 and positive FY27 operating cash flow, and says inventory and receivables should convert as EPC billing resumes. Capital allocation so far is disciplined on paper: the Kharagpur land approval in principle for approximately 40 acres is a plank for higher-value transmission products, but capacity, capex and funding are undecided, and management said scale and timing will follow demand visibility and expected returns.

The 18-24 month picture, as management frames it rather than as a forecast, is a company with two new transmission credentials in hand, a manufacturing base of about 85,400 metric tons running at roughly 70-75% utilisation, and a finance cost burden that steps down through the post-repayment quarters. The falsifiers are specific. First, no follow-on HTLS or extra-high-voltage orders beyond the first Power Grid and CESC contracts, leaving specialised products too small to shift mix while a 15-16% revenue growth anchor is not being delivered at the current 2-7% run-rate. Second, working capital that fails to improve by the targeted 25-40 days by Q4 FY27, keeping operating cash flow negative and requiring further borrowings. Third, Kharagpur capex committed ahead of confirmed demand onto an already under-utilised base. Fourth, the FY28 resumption of cash tax after the FY23 acquisition carry-forward losses are exhausted, which raises the bar for reported PAT growth. Guidance is explicit on margin, H2 interest savings, working capital days and positive FY27 operating cash flow; the revenue growth rate and the HTLS pipeline conversion are inference from order intake and history, not stated targets.

Why is Laser Power & Infra Ltd stock rising?

  • Power Grid awarded a contract aggregating INR72.76 crores for supply of HTLS conductors and re-conducting of existing transmission lines, Laser's first commercial HTLS order. Management said the advanced conductor platform has moved from development qualification to commercial execution after roughly 18 months of product testing, qualification and execution readiness, and called the award commercial validation of that effort.
  • CESC awarded a INR44 crores order for EPC work involving 33 kV and 220 kV underground cabling, Laser's first 220 kV underground transmission project, with roughly one year of execution. Management said extra-high-voltage underground cabling is increasingly needed in dense, land-constrained cities and that successful execution would add credentials and position the company for similar larger opportunities.
  • Approximately INR490 crores of IPO proceeds were used to repay borrowings during Q2 FY27, leaving total borrowings of approximately INR499 crores on September 30, 2026. Q2 finance cost was approximately INR33 crores, down from INR36 crores in Q1 FY27 and INR34 crores in Q2 FY26. Management said the interest cost saving will reflect more fully in H2 FY27 and, with better operating performance, could support PAT margin improvement.
  • Manufacturing revenue was INR524 crores in Q2 FY27 against INR404 crores a year earlier, a 29.9% increase on higher manufacturing activity and dispatches, while EPC revenue fell to INR104 crores on rain-related execution delays. Consolidated EBITDA was INR76 crores at a 12.1% margin, and management guides the FY27 margin to stabilise at 12.5-13%.
  • Working capital days reduced to 166 from 183 in Q1 FY27 even as absolute working capital rose to approximately INR1,159 crores. Management targets a 25-40 day reduction in working capital days by Q4 FY27, expects inventory and receivables to convert as execution and billing resume, and expects operating cash flow to turn positive for FY27.

Research report

companyname: Laser Power & Infra Limited ticker: LASERPOWER sector: Power Transmission & Distribution (Manufacturing + EPC Infrastructure) Laser Power & Infra Limited is a power transmission and distribution company that runs manufacturing and EPC as one integrated business. It started more than three decades ago and listed in July 2026. The integrated model is the point. The company makes cables, conductors, and specialty products at three plants in Eastern India, then uses those same products...

Read the full report →

Catalysts

acquisition inorganic, debt reduction

Growth guidance

Management guides FY27 H2 EBITDA margin to stabilise at 12.5-13%, expects the interest cost saving from the IPO-funded debt repayment to reflect more fully in H2 and, together with better operating performance, to support overall PAT margin improvement in H2, expects operating cash flow to turn positive for FY27, and targets a 25-40 day reduction in working capital days by Q4 FY27. It also expects further order book improvement by year-end. Typical margin reference points given are 10-11% for manufacturing and 14-16% for EPC projects, with about 40-42% of full-year revenue normally booked in H1.

Get valuation models, detailed research reports, thematic primers, risk analysis, growth triggers, bear case, capex tracker, walk the talk, and more for Laser Power & Infra Ltd and 4,900+ companies.

Sign in
5-day free pass. No card required.